The Goodwins Island Wind Farm Project is situated near Lower Woods Harbour in Shelburne County, Nova Scotia. The Schneider Power Management Team believes this project has a potential wind power capacity of up to 20 MW.
Environmental, wind resource and engineering studies respecting this project have been commenced, including an environmental impact study and most of the required municipal, transport Canada and NAV Canada approvals have been obtained. Interconnection to the transmission grid is dependent on the construction of a 2.5 km feeder line to the existing distribution line.
Schneider Power has made an application with Nova Scotia Power for a connection study for up to 20 MW of capacity and is anticipating the results of the study to be completed by late 2009.
The Goodwins Island Wind Farm Project is situated on land owned by Schneider Power.